S.No. | Activity (Code) | Name of the work activity wise | Location | Approved outlay for 2020-21 |
Revised Estimates
2020-21 |
Funds released during
2020-21 |
---|---|---|---|---|---|---|
1 | 16100030 | Providing/Laying of 150MM Thick Wet Mix , 50MM Thick Macadam and 25MM Thick Semidense including 6MM Thick Seal Coat OF MUGHAL ROAD including road line marking (A) From Buffliaz Side = RD 0+00 to RD 43+600 BT Work (B)From Shopian Side KM (RD 0+000 to RD 40+550 BTwork) | Buffliaz (Poonch Side):-
Km 13+000 to 20+000
Km 27+000 to 33+000 KM 35+000 to 43+600 Shopian Side:- Km 0+000 to 9+000 Km 25+000 to 40+550 |
2500.00 | 2200.00 | 1250.00 |
2 | 16100013 | Providing /laying of create work for retaining of slopes at required spots. (a). From Pushana to Pir Ki Gali =4.00KM (b). From Pir Ki Gali to Dubjan =2.50KM | Buffliaz Side :-
Km 38+000 to 43+600 Km 11+000 to 27+000 Km 32+000 to 38+000 Km 5+500 to 11+000 Km27+000 to 32+000 |
150.00 | 160.00 | 150.00 |
3 | Add W.C Contingencies and Consultancy Charges @3% | - | 30.00 | 50.00 | 0.00 | |
4 | Clearance of snow at spots by MED , MED Claim for Clearance of snow during 2019-20 /Spreading of salt after clearance of Snow .
Km 0+00 to 40+550 (Shopian Side) Km 0+00 to 43+600 (Buffliaz Side) |
KM 84.10 | 40.00 | 50.00 | 0.00 | |
5 | Removal of Slips/Slides/Surcharge/De-Silting of Culverts./Restoration of damaged Berms/ Clearance/clearanceof drains at various /Cloud Burst/Clearance of deposited Mulba from Choked Culverts, spots. | Buffliaz (Side)
km 1+050 to 1+076 km 1+650 to 1+670 km 2+120 to 2+910 to 3+930 km 16+000 to 22+000 km 15+580to 15+612 km 16+980 to 17+005 km 20+150 to 20+230 km 20+700 to20+750 km22+00 to 27+000 km 2+380 30+740 to 30+850 km 31700 31+780 km32+00 to 3500+00 km 40+920 to 41+120 Shopian Side :- Slips/slides/culverts: 12+000 to 38+000 Berms/Drains: 0+000 to 3+000 |
240.00 | 220.00 | 0.00 | |
6 | Reconstruction/Construction of R/Wall, B/Wall at various spots/Construction of Gabion Walls at various locations incld. Cost of Gabions and cost of soil /Filling of stones into wire mesh crates for stabilization of soil/Fixing of kilometre stones /RD Stones/Construction of damaged railing of Bridges/Painting/Construction of PCC drains at various spots/Fixing of Crash Barriers incld. Retro reflective films at spots/ | R/Walls:
40+920 to 41+120 B/walls: 12+000 to 30+000 Gabbions: 16+000 to 19+000 Crash Barrier: 0+600 to 6+000 13+000 to 18+600 22+000 to 27+000 29+000 to 31+000 31+000 to 36+000 PCC Drains: 4+000 to 8+000 |
270.00 | 160.00 | 0.00 | |
7 | Repair of damaged sign boards and supply/fixing of new sign boards/Repairs of passengers shed constructed along the road/Construction of parapets over the existing R-wall at required spots/Construction of temporary diversions at various spots/Repair/Maintenance/Construction of CD works/Repair/Renovation of Buildings etc./Constt of Snow Dett . | Repair and revovation of Vip Hut Chandimarh
Repair and revovation of VIP Hut Surankote Repair and Revovation of Divisional Office Surankote Repair of Snow dett. Sign boards 2+000 to 40+550 Parapets 12+000 to 32+000 Buildings: Lalmandi Srinagar, chowgam shopian, dubjan, Pir-Ki-Gali |
60.00 | 80.00 | 0.00 | |
8 | Provision for improvement of Bye-Pass at Avalanche Prone Stretche/Improvement of damaged Road Surface b/w of GSB filling & P/L of WBMG-II in Patches /Stretches & Rectification of Damaged road Surface b/w of P/l 50 mm Thick macadam & 25 mm thick semidence in patches/stretches and Re-allignment of Road from RD 0+000 to15+000 (Buffliaz Side) RD: 19+200 to 19+600 (Dubjan Curve Shopian Side). | Km, 0+000 to 40+200 , 2+600 to 2+740
Dubjan curve 19+200 to 19+600 |
160.00 | 250.00 | 0.00 | |
9 | Rectification of damaged road surface on temporary basis | 9+000 to 25+000 | 20.00 | 25.00 | 0.00 | |
10 | Widening of Blind Curves at Accidential prone areas at various spots. | 30.00 | 27.00 | 0.00 | ||
Total | 3500.00 | 3222.00 | 1400.00 |