  • TRANSIT ACCOMMODATION

TRANSIT ACCOMMODATION

STATUS OF TRANSIT ACCOMMODATION ENDING FEBRUARY 2021

S.    No District Location No. of flats to be constructed DPR cost (Rs in Crore) Present status of work ending Feb 2021
  R&B        
1 Srinagar Zewan (Pantha Chowk) (Kahcharai  land) 480 59.88 Initially DPR of Rs. 7549.46 lacs submitted to Department of Disaster Management, Relief Rehabilitation & Reconstruction (DDMRRR) for Accord of AA on SSR rates 2020. 

DDMRRR returned the said DPR with the some observations, as the per cost per flat was exceeding the DPR cost of Rs. 12 lacs. 

Fresh DPR  submitted to DDMRRR vide CE R&B Kashmir letter dated 21-01-2021 for an amount of Rs. 5988.20 lacs for 480 flats for Accord of AA. 
2 Ganderbal Wandhama A- Lar (Sumbal Kangan Highway) 192 23.04 Superstructure in progress. 41% work completed.
3 Ganderbal Khalmula Baba daryadin 192 23.45 Fresh DPR submitted to DDMRRR for an amount of Rs. 2345.18 lacs for 192 flats for Accord of AA.
Land measuring 29 kanals 4 marlas handed over to Assistant Ex. Engineer, PWD Ganderbal (executing agency)  by Tehsildar Relief & Rehabilitation (M) Kashmir vide No DRR(M)Sgr/20-21/522-528 dated      01-03-2021
4 Bandipora Odina Sumbal 480 57.6 Fresh tenders again invited vide NIT 62 dated 03.03.2021 for Group A, B and C (Block 1 to 30). 
Date of receiving tender 16.03.2021.
5 Baramulla Fatehgarh Baramulla.  336 40.9 GAD vide Govt. Order No. 38-JK(GAD) of 2021 dated 18-01-2021 has constituted of Auction Committee for 13 no. of Govt structures 
Auction process completed, dismantling work being started. Fresh tender again invited vide NIT No 149 dated 25-02-2021 for A, B, C, D & E blocks. Date of receiving tender 22-03-2021.
Land measuring 40 kanals handed over to Assistant Ex. Engineer, PWD Baramulla (executing agency)  by Tehsildar Relief & Rehabilitation (M) Kashmir vide No DRR(M)Sgr/20-21/529-35 dated 02-03-2021
6 Kupwara Kulan baghgam 288 34.56 Fresh tenders invited vide NIT No. 39 dated 18-01-2021 Block (1 to 6) Group A, Block (07-12) Group B, & Block (13 to 18) Group C (Date of receiving  09-02-2021)
Technical Evaluation in final stage.
7 Kupwara Natnoosa     Land not transferred as yet.
8 Anantnag Sangam Marhama Bijbehara 192 23.04 Land identified / transferred 13 kanal and 16 marla at Marhama Bijbehara Anantnag remains inundated during the rainy season. So, ground floor is proposed to be converted into stilt (parking) which will reduce the number of flats from 16 to 12 per block, thus the outcome of the project will get reduce from 192 flats (1BHK) to 144 flats (1BHK) and the cost of per flat exceeded  beyond 12 lacs limit.
Now, DDMRRR has requested Divisional Commissioner Kashmir to identify the alternative piece of land measuring 30 Kanal in District Anantnag instead of already transferred land.
9 Anantnag Mattan 240   50 Kanals Land identified.
Land measuring 35 kanals 10 marlas handed over to Assistant Ex. Engineer, PWD Anantnag (executing agency)  by Tehsildar Relief & Rehabilitation (M) Kashmir vide No DRR(M)Sgr/20-21/546-51 dated                  05-03-2021
10 Pulwama Barsoo near CTC 448 57.54 Initially DPR forwarded to DDMRRR vide CE R&B Kashmir letter dated 29-10-2020 for an amount of Rs. 4430.55 lacs for accord of AA.
DDMRRR returned the said DPR with the some observations, as per cost per flat was exceeding the DPR cost of Rs. 12 lacs. 
Fresh DPR  submitted to DDMRRR vide CE R&B Kashmir letter dated 21-01-2021 for an amount of Rs. 5754.32  lacs for 448 flats for Accord of AA.
Revised DPR forwarded to DDMRRR for 6 stories apartment block (G+5) instead of (G+3) for Rs 6424.27 lacs in light of DDMRRR letter dated 16-02-2021 and verbal directions of Chief Secretary.
11 Shopian Allopwora Keegam. 192 23.04 Earth excavation completed for 3 blocks.
Soiling & mudmatt completed for 3 blocks,                        
Reinforcement for raft, foundation beams and columns completed for first block
Reinforcement for raft completed for second block (work in progress)
      3040 343.05  
  JKPCC        
1 Budgam Sheikhpora  96 28.53 Block C, D, E & F completed & handover.
Block "A" Completed .
Block "B" Structure completed. Interior finishing work is in progress. 
Building illegally occupied by Migrants from 6th August 2019.
2 Kulgam Vessu Phase-1st 512 136.8 Block A, B & C:- Completed & occupied by Migrant Employees & Security Forces from 19-06-2018.
Block "G & H":- RCC frame work completed. Brick work, Plaster & Truss work completed. Sanitary & finishing work in progress. 
Block"3B":- RCC frame work, Brick work / truss work/ Plaster work & CGI Roofing completed. Finishing work is in progress.
Block "K":- Framed structure / Brick work completed.  Finishing work / Truss work is in progress.
Block "D":- Framed structure / Brick work / Plaster work / Truss work & CGI Roofing completed. Finishing work in progress
Block "I":- Frame structure, Plaster work , Truss & roofing completed. Finishing is in progress.
Block "J, 4B & E":- Framed structure completed. Brick work is in progress.
Block "F":- Frame structure completed.
Boundary Wall:-  completed.
3 Anantnag Shangus  320 40.9 Cost Offer submitted to Project Authority for Accord of Administrative Approval.
4 Anantnag Machbawan  240 31.2 Cost Offer submitted to Project Authority for Accord of Administrative Approval.
5 Srinagar Zewan  624 79.25 Cost Offer submitted to Project Authority for Accord of Administrative Approval.
6 Kupwara Khullangam Bagh 288 38.27 Cost Offer submitted to Project Authority for Accord of Administrative Approval.
7 Budgam Ichgam 192 23.04 Cost Offer submitted to Project Authority for Accord of Administrative Approval
      2272 377.99  
  G. TOTAL   5312 721.04