Physical/Financial Status of JTFRP Projects upto ending 01-01-2020   (FIRE & EMERGENCY DEPTT)

S.No Identified Activity/Work District DPR Cost INR Lacs Revised Cost INR Lacs AllotmentCost
INR
Lacs
 Project commencement Year Funds released upto ending 03-2020  INR
Lacs
Expenditure Upto ending 03/2020 INR
Lacs
Funds Released (2020-21) Ending 11-2020 INR
Lacs
Physical Status in %age Present Physical
Status
12 Construction of Administrative Block and Store Building at Fire & Emergency Services Headquarter Batmaloo, Srinagar, J&K.             Srinagar  906.70 - 906.70 2020 0.00 0.00 0.00 14.34 For Admin block, Raft Foundation  Completed. Work on plinth beam & columns in progress                                              For store building, Excavation pending due to  realignment of SMC drain
  Total       906.70   0.00 0.00 0.00