Physical/Financial Status of JTFRP Projects upto ending 01-01-2020      (HEALTH DEPTT)

S.No Identified Activity/Work District DPR Cost INR Lacs Revised Cost INR Lacs Allotment Cost
INR
Lacs
 Project commencement Year Funds released upto ending 03-2020  INR
Lacs
Expenditure Upto ending 03/2020  INR Lacs Funds Released (2020-21) Ending 11-2020  INR Lacs Physical Status in %age Present Physical
Status
13  Design, Construction and AMC of 120 Bedded Specialized Orthopaedic Units Including Six Bedded ICU in Bone & Joint Hospital in Srinagar             Srinagar 8894.00 - 8894.00 2019 782.00 782.00 0.00 6.27 Structural design of foundation partly  vetted by NIT Srinagar.                                                     172 No of Piles completed  out of 287 No casted, IGBC/local body permissions in progress. UG tank and STP Design finilized (Pending for approval from NIT Srinagar).  working Pile load test completed. 
  Total       8894.00   782.00 782.00 0.00