HIGHER EDUCATION - Physical/Financial Status of JTFRP Projects upto ending 01-01-2020     


S.No Identified Activity/Work District DPR Cost INR Lacs Revised Cost INR Lacs Allotment Cost
INR
Lacs
 Project commencement Year Funds released upto ending 03-2020  INR Lacs  Expenditure Upto ending 03/2020  INR Lacs Funds Released (2020-21) Ending 11-2020  INR Lacs Physical Status in %age Present Physical
Status
7 Construction of Science Block at Amarsingh College Srinagar                   Srinagar   719.11 - 719.11 2019 33.95 33.95 226.23 50.06 2nd slab for. Upper ground floor slab completed. Work for 1st floor colums in progress. 
8 Construction of Classroom Block at Women College, M.A road Srinagar.  Srinagar   1334.31 - 1334.31 2019 0.00 0.00 390.00 44.22  Pileraftcompleted ,Plinth beams completed, work for stilt floor columns in progress. 
9 Construction of Administrative block at GDC for Women,Anantnag.   
Anantnag 
251.00 - 251.00 2019 0.00 0.00 5.00 18.90 Form work for stilt floor slab/beam in Progress. 
10 Construction of Additional Classroom Block at GDC Bijbehara.
Anantnag 
921.97 - 921.97 2019 175.00 175.00 155.00 39.50 Two slabs laid (of Stilt floor & Upper ground floor slab). Reinforcement of  second floor in progress. 
11 Construction of humanities block at GDC Bemina.   Srinagar   894.48 - 896.48 2019 44.80 44.80 196.41 25.16 Raft foundatoin completed. Short colunms upto plinth beam completed. PCC block in periphery of the building completed. Concreting of plinth beam in progress. 
Construction of staff room and meeting hall block at GDC Bemina  1st and 2nd floor slabs completed. Truss work delivered at site. 
  Total 06 Works     4122.87   253.75 253.75 972.64