S.No | Identified Activity/Work | District | DPR Cost INR Lacs | Revised Cost INR Lacs |
Allotment Cost INR Lacs |
Project commencement Year | Funds released upto ending 03-2020 INR Lacs | Expenditure Upto ending 03/2020 INR Lacs | Funds Released (2020-21) Ending 11-2020 INR Lacs | Physical Status in %age |
Present Physical Status |
1 | Sadoora Bridge (3x30 mtr) on Ashajipora Kamad Sadoora Road | Anantnag | 631.00 | - | 631.00 | 2020 | 0 | 0 | 0 | 2.00 | Designs vetted by NIT on 28.09.20 RCC work of abutment on Sadoora site completed upto 40% level. Earthwork excavation for abut A2 (kamand side) completed. |
2 | Kalaiban Bridge (1x25 mtr) | Baramulla | 263.90 | - | 263.90 | 2020 | 26.39 | 26.39 | 0 | 24.00 | Designs vetted by NIT on 11.06.20 Both abutments completed. Shuttering of cap beams in progress. |
3 | Wayil Bridge (110 mtr) over Nallah Sindh at Ganderbal | Ganderbal | 2379.00 | - | 2379.00 | 2020 | 237.90 | 237.90 | 0 | 0.50 |
Designs vetted by NIT on 18.09.20
Old
Existing Abutment dismantalled. Old Existing Tilted well dismantlled. Fabrication of cutting edge completed. |
4 | Chamgund Bridge (400 mtr) | Kulgam | 3240.05 | - | 3240.05 | 2020 | 324.00 | 324.00 | 0 | 4.00 | Designs vetted by NIT on 02.10.20 Raft of pier No. 06 completed. Reinforcement of pier No. 06 shaft completed and shuttering in progress of first lift (2.2 mtr). Excavation for pier No. 03 raft is complete and preperation of laying of mudmat in progress. |
5 | Watchi Bridge (1x45 mtr) at Kumar Mohalla | Shopian | 311.00 | - | 311.00 | 2020 | 0 | 0 | 0 | 0.50 |
Designs vetted by NIT on 11.06.20
Test pile failed under load test and report
submitted to designer for re-design.
|
6 | 4x 35 mtr Span double lane Bridge at Aripathan Rutson | Budgam | Not taken up due to non feasability of site | ||||||||
Total | 05 Works | 6824.95 | 588.29 | 588.29 | 0.00 |