• Home
  • World Bank projects

Physical/Financial Status of JTFRP Projects upto ending 01-01-2020        (BRIDGES)

S.No Identified Activity/Work District DPR Cost INR Lacs Revised Cost INR Lacs Allotment Cost
INR
Lacs
 Project commencement Year Funds released upto ending 03-2020  INR Lacs  Expenditure Upto ending 03/2020  INR Lacs Funds Released (2020-21) Ending 11-2020  INR Lacs Physical Status in %age Present Physical
Status
1 Sadoora Bridge (3x30 mtr) on Ashajipora Kamad Sadoora Road Anantnag       631.00 - 631.00 2020 0 0 0 2.00 Designs vetted by NIT on 28.09.20                                                          RCC work of abutment on Sadoora site completed upto 40% level. Earthwork excavation for abut A2 (kamand side) completed. 
2 Kalaiban Bridge (1x25 mtr) Baramulla 263.90 - 263.90 2020 26.39 26.39 0 24.00 Designs vetted by NIT on 11.06.20            Both abutments completed. Shuttering of cap beams in progress.                                                                 
3 Wayil Bridge (110 mtr) over Nallah Sindh at Ganderbal Ganderbal 2379.00 - 2379.00 2020 237.90 237.90 0 0.50 Designs vetted by NIT on 18.09.20                                                                     Old Existing Abutment dismantalled.
Old Existing Tilted well dismantlled.
Fabrication of cutting edge  completed.
4 Chamgund Bridge (400 mtr) Kulgam 3240.05 - 3240.05 2020 324.00 324.00 0 4.00 Designs vetted by NIT on 02.10.20                                                               Raft of pier No. 06 completed. Reinforcement of pier No. 06 shaft completed and shuttering in progress of first lift (2.2 mtr). Excavation for pier No. 03 raft is complete and preperation of laying of mudmat in progress. 
5 Watchi Bridge (1x45 mtr) at Kumar Mohalla  Shopian 311.00 - 311.00 2020 0 0 0 0.50 Designs vetted by NIT on 11.06.20    Test pile failed under load test and report submitted to designer for re-design.                                                             
6 4x 35 mtr Span double lane Bridge at Aripathan Rutson  Budgam                 Not taken up due to non feasability of site
  Total 05 Works     6824.95   588.29 588.29 0.00